OPENING REMARKS:
Chairman Brannen opened the meeting at approximately 7:00 p.m.
expressing appreciation for those in attendance and requested
roll call.
ROLL CALL: Commissioners: Bill Corroum, Bobby Lester, Bart Gray
Jr., Dean Wilborn, and John Hardwick answered ROLL CALL.
Chairman Brannen also answered ROLL CALL. PRESENT five (5),
ABSENT (1).
Others present for the meeting were City Engineer Whisker and
Patriot Reporter Peggy Koury.
Chairman Brannen accepted Commissioner Hardwick and Commissioner
Lester as volunteers serving from the Planning Commission for
2001 Board of Adjustment appointments.
APPROVAL AND/OR CORRECTION OF MINUTES:
Commissioner Corroum moved, seconded by Commissioner Lester that
the minutes of the 13 November 2000 Regular Planning Commission
meeting and the 27 November 2000 Special Planning Commission
meeting be APPROVED. MOTION CARRIED.
REQUEST TO ACCEPT PLAT(S):
a. FINAL PLAT Collenwood Subdivision PH II
Mr. Jim Green related the plat changed only by the addition of
three or four lots from the preliminary plat presentation.
City Engineer Whisker clarified that the preliminary plat
included the remaining development area and Phase II is a
portion of that remainder. He related that changes included
Jamestown Circle which now stops as it connects to Colonial
Drive and the Bill of Assurance added the wording that the
property owners association had to meet with the flood plain
manager regarding construction in the flood way. He pointed out
that the flood way is located at the rear of lots 48, 49, 50 and
51.
Mr. Green then related that none of the lots actually encroaches
on the flood way.
Chairman Brannen questioned the F designation for lots 45, 46,
47 and 94.
City Engineer Whisker clarified that the line from lot 31 and
the one already created through 47 through 51 is the flood way
boundary, adding that directly south is the Stonewall ditch and
the ditch creates the flood way zone, so the area between
1
Colonial Drive and Stonewall is a flood way.
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
It was noted that the ditch is directly behind lots 50, 51, and
49.
Mr. Green further clarified that it is approximately three or
four hundred feet and that the ditch runs southeast/northwest.
He noted that the plat did not include a scale and that for
reference purposes, Jamestown Circle is within a minute or so of
due north and south.
Commissioner Hardwick recalled that the original subdivision
plans required fences in the rear of lots located on J.P. Wright
Loop, which would now be lots 70 through 66 of Phase II. He
questioned initial action regarding fences for those lots.
Mr. Green stated that he does plan to continue with previous
fence stipulations regarding lots 66 through 70.
City Attorney Bamburg advised that it should be included as part
of the approval as a requirement.
City Engineer Whisker asked that approval also be contingent
upon his approval regarding readiness to send the item to City
Council.
Discussion ensued regarding sidewalk requirements and it was the
general consensus that the Master Sidewalk Plan was adopted
after the approval of the Preliminary Plat for Collenwood
Subdivision.
Commissioner Hardwick noted that there was always a sidewalk
plan, but was somewhat ignored and agreed that the preliminary
plat was approved prior to the revision of those guidelines. He
stated that he did not feel it would be wise to place sidewalks
that do not lead anywhere at this point.
Commissioner Gray stated that the Ordinance requires sidewalks
of all developers.
Commissioner Hardwick related that it is a requirement of new
plats being approved, but he felt it was not intended to be
retro for plats that were previously approved regarding second
and third phases because the sidewalk would not connect or lead.
City Engineer Whisker pointed out that the preliminary plat of
Collenwood included the remainder of that subdivision not just
phase II, which will be further broken out later with Phase III.
2
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
Further discussion ensued and City Engineer Whisker related that
preliminary plat approval stands for one year as long as Phase
III begins within one year. He stated that he would research if
it actually has to be finished or just in construction.
Commissioner Gray pointed out that support data indicated that
the preliminary plat for Collenwood Phase II was approved
November 8, 1999.
It was then noted that water, sewer, and fire has given plat
approval to the City Engineer.
Commissioner Hardwick moved, seconded by Commissioner Wilborn to
approve the Final Plat of Collenwood Phase II, stipulating that
fences be erected on lots 66 through 70 as with Phase I and
further stipulating that if the Master Sidewalk Plan calls for
sidewalks it would not require them in phase II, as it does not
appear to be practicable for this development to place sidewalks
that do not lead or connect and further subject to the City
Engineer’s final approval. MOTION CARRIED.
b. FINAL PLAT Gene Wilson Commercial Development
Mr. Wilson related that he is scheduled to close Thursday on one
of the two tracts involved in the final plat.
City Engineer Whisker related that the property is located south
of Kroger on North First Street. He stated that lot 1 currently
has a small green house located there and lot 2 has a duplex on
the corner with a gravel drive leading back into the mobile home
park behind both pieces of property. He further related that an
auto parts store is planned for lot 2, and the final plat will
create the subdivision and plat the 30-foot easement owned by
the Mr. Wilson as access to the mobile home park.
Commissioner Gray recalled several discussions in the original
review and in Board of Adjustment considerations for the auto
parts store and it was recommended that the property be platted
as a joint access off Hwy 161 for both lots.
City Engineer Whisker agreed and stated that the building permit
would be the last action for lot 2 after it becomes a
subdivision adding that a building permit in a subdivision does
not have to go through the Planning Commission.
Commissioner Gray suggested that consideration for one turning
3
in access for both lots as a stipulation needs to be addressed
at this time.
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
City Engineer Whisker suggested that the bill of assurance could
provide an avenue for that provision.
Mr. Wilson pointed out that the property actually has three
entrances.
City Engineer Whisker stated that the current discussion suggest
that the parking area of both lots should share all three
entrances, connecting the parking areas behind the sidewalks so
that a vehicle pulling into lot 2 can drive through to lot 1.
Commissioner Gray explained that currently there is access on
the north side, behind the grocery store and one on the south
part of lot 1 to the mobile home park, adding that the
recommendation will only be for one additional turning into both
lots. He clarified that the two driveways would be consolidated
into one driveway for both lots.
Discussion ensued and Commissioner Hardwick stated that the
objective of the Planning Commission is for two driveways,
pointing out that while there are three curb cuts, two of them
are single family residents. He then stated that because of the
traffic generated from a commercial development this stretch of
Hwy 161 does not need three curb cuts to access these
properties. He stated there would be an access to lot 1, lot 2
and access to the mobile home park, adding that it could be
structured for a shared access between lot 1 and 2, or where the
only access to lot 2 is from the easement then we can accomplish
two curb cuts as opposed to three. He concluded that he felt it
would be a traffic hazard to have three curb cuts for these two
lots.
Discussion ensued regarding the location of the third curb cut
being at Gregory Place and City Engineer Whisker stated that it
was his understanding that there would be three curb cuts and
the middle one would be a shared access by the two lots.
Commissioner Gray mentioned the alley behind Gregory Place
adjoining the property and Commissioner Wilborn asked it a fence
was between the properties and Kroger.
Mr. Wilson responded that there is an alley behind Kroger and
that the north line has a fence, adding that half of the forty
foot curb is in the alley and half is on his property as a
continuous shared curb cut.
4
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
In response to a question from Commissioner Wilborn, Mr. Wilson
related that the location of the road that leads to the trailer
park is not a center access, adding that the center access point
lead behind his house.
It was noted that the road on the south side is the road that
goes into the mobile home park.
Mr. Wilson then responded that the mobile home park easement is
going to be turned into a street.
City Engineer Whisker questioned and clarified with Mr. Wilson
that the new owners of lot 2 are going to asphalt the
utility/access easement back to the west property line and that
it will be maintained by the property owner.
Mr. Wilson stated that easement maintenance will be shared with
the owner of lot 2 and is covered in the bill of assurance.
City Engineer Whisker quoted the bill of assurance as saying
“will be the responsibility of the owner to maintain, and no
utility and/or public agent will be liable for destruction of
same in constructing and maintaining its facilities located
within the area of said easement.” He stated that it speaks
specifically to the area of the easement and that as stated it
places the responsibility to the owner to maintain.
Mr. Wilson responded that the bill of assurance needs to be
changed because the easement agreement stated that it would be
shared.
City Attorney Bamburg reminded that the a bill of assurance
covenant is for 30-years and City Engineer Whisker added that it
extends itself every ten year after unless changed.
City Attorney Bamburg clarified that the mobile home park is not
a part of the subdivision and it was related that the owners of
lot 1 and 2 could decide that the owner of the mobile home park
does not have to maintain the road at the end of 30-years.
Discussion ensued and Mr. Wilson stated that the bill of
assurance will need to be changed for a shared maintenance
agreement.
5
City Engineer Whisker stated that it is his understanding that
the bill of assurance is accepted along with final plat
approval.
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
Commissioner Gray stated that as a common agreement it needs to
be addressed.
In response to a question from Commissioner Gray, Mr. Wilson
agreed to revise the bill of assurance, adding that he requested
the road be developed to City specifications because of truck
access and future repairs.
Discussion ensued and it was noted that both parties must agree
to changes of the bill of assurance regarding shared maintenance
for the access.
Commissioner Hardwick offered that it would be beneficial to all
parties to redraw the bill of assurance and have it state that
the access to lot 2 includes an easement to lot 1 from the
street to the building setback line. He explained that if lot 1
is granted an easement to the building setback line regarding
the present curb cut then there would be no need for lot 1 to
request an additional curb cut.
Discussion ensued and it was related that lot 1 is currently for
sale as commercial property.
Commissioner Hardwick moved, seconded by Commissioner Lester to
table the item of business pending Mr. Wilson’s return with a
revised bill of assurance, drawn as he intended on the present
easement regarding access to the mobile home park by showing it
to be shared maintenance between lot 2 and the mobile home park
and to show an easement to lot 1 on the north side of lot 2 to
the building setback line regarding the 40-foot drive and that
the bill of assurance would also state that after the 30-year
period the easement maintenance to the back line of lot 2 would
fall upon the owner of lot 2.
Commissioner Gray asked Mr. Wilson if waiting until the next
meeting date would create a hardship. Mr. Wilson responded that
he did not know, reiterating that the close date is Thursday
th
before the January 8 City Council meeting.
Discussion ensued and it was suggested that final plat could be
approved specifying all stipulations.
Commissioner Gray stated that the final plat can not be recorded
6
until the City Council approves it, which is still almost two
weeks after the closure date.
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
When asked about his thoughts, Mr. Wilson stated that he was not
sure regarding his next action but wanted finality. He then
stated that the bill of assurance would be changed quickly but
added that he would need to get with the future owners of lot 2
regarding a shared access between lot 1 and 2. He stated that
if a shared access could not be worked out, it renders the deal
useless. He also mentioned waiting for City Council approval.
Discussion ensued and it was noted that as the motion stands the
Planning Commission would have to meet again for approval before
recommendation to the City Council. It was then discussed if
the closing date could be reset regarding time for final plat
approval.
Commissioner Wilborn clarified that the only real question is if
the owners of lot 2 will allow a shared access with lot 1 and
the bill of assurance regarding maintenance responsibility for
the easement.
Discussion ensued as to a special called meeting of the Planning
Commission regarding final plat approval. Mr. Wilson did not
know if it would be a problem to change the closing date.
Commissioner Hardwick moved, seconded by Commissioner Lester to
amend the previous motion and approve the final plat of the Gene
Wilson Commercial Subdivision with the conditions that the
paragraph one of the bill of assurance be changed to show the
shared cost of the utility/access easement for the first 30-
years, and then the cost to be the responsibility of the owners
of lot 2 after that 30-year period; and further that the bill of
assurance include an easement to lot 1 from the curb cut on the
north side of lot 2 back to the 50-foot building line, with the
plat showing the same.
Consensus was that the amended paperwork would be delivered to
the City Engineer.
Discussion ensued and it was determined that based on the
wording of the motion a special Planning Commission meeting
prior to the City Council meeting would not be necessary if all
stipulations are met.
MOTION CARRIED.
7
GENERAL: Discussion of proposed west and south Annexations
City Engineer Whisker presented a map regarding the south
annexation and explained the approximate new boundaries if
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
annexed. He related that the annexation would include St.
Luke’s Church, a few houses on Hwy 161, part of the cemetery,
and one or two businesses along Hwy 161. He related that he is
currently contacting property owners. He announced that the
th
public hearing annexation meeting will be held January 8 at
6:00 p.m. at City Hall. He related that the Water and Sewer
Departments will be in attendance to answer questions.
He then related that an aerial photo and legal description
regarding the west annexation proposal was previously
distributed.
Discussion ensued and it was related that the public hearing
will cover both the west and south annexation proposals.
City Engineer Whisker mentioned consideration for the Federal
Grant involving the Wooten Road area regarding wastewater. He
then mentioned that an area of property from the cemetery to the
liquor stores would remain in the County. He stated that a
private club located on Hwy 161 will be included in the south
annexation. It was further discussed and consensus was to
determine if it was a private club or open bar.
City Engineer Whisker related that his understanding is that the
south annexation is a result of efforts to annex the northbelt
freeway and a portion of the Hwy 161, adding that this is
accomplished by following the railroad tracks and the section
line.
Commissioner Gray suggested that a property owners map be made
available for the public hearing.
City Engineer Whisker stated that some of the boundary line
follows property owner lines as well as section lines as they
coincide. He pointed out that the boundary line does not split
property owners’ land except a property owner on the north
section by the church to the railroad tracks and AP&L’s property
on the south end divided by the section line where the property
continues to extend southward.
City Attorney Bamburg stated that the annexation process would
depend on input from the various property owners involved in the
proposed annexed area.
8
Commissioner Corroum stated that with the completion of the
northbelt freeway; Hwy 161 is going to become a major
thoroughfare with possibility of additional annexation
proposals.
CITY OF JACKSONVILLE, ARKANSAS
REGULAR PLANNING COMMISSION MEETING
DECEMBER 11, 2000
7:00 P.M. - 8:05 P.M.
Commissioner Hardwick stated that current proposal is less
likely to receive objections.
In response to a comment from Commissioner Corroum, City
Engineer Whisker related that the Police Department currently
patrols the landfill area and he will check regarding the area
south of there.
Discussion ensued regarding the proposed annexation for Maddox
Road and Pridmore and it was related that it was not included in
the current annexation public hearing.
ADJOURNMENT:
Chairman Brannen without objection adjourned the meeting at
approximately 8:05 p.m.
Respectfully,
Susan L. Davitt
Planning Commission Secretary
9